Primavera Project Planner - P3 Member for 22 years 9 months Member for 22 years 9 months Submitted by Alex Wong on Thu, 2006-12-14 18:55 Permalink RE: MAking Additonal progress Bar... Create a copy of exisiting schedule Make it your target schedule Display your target bar Modify your target schedule or Current schedule that way the other wont change. Normally you modify your current schedule and maintain the target as a baseline Good Luck ALex Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alex Wong on Thu, 2006-12-14 18:55 Permalink RE: MAking Additonal progress Bar... Create a copy of exisiting schedule Make it your target schedule Display your target bar Modify your target schedule or Current schedule that way the other wont change. Normally you modify your current schedule and maintain the target as a baseline Good Luck ALex
Member for
22 years 9 monthsRE: MAking Additonal progress Bar...
Create a copy of exisiting schedule
Make it your target schedule
Display your target bar
Modify your target schedule or Current schedule that way the other wont change. Normally you modify your current schedule and maintain the target as a baseline
Good Luck
ALex