Actual earned quantity!! Not match with real situation!

Member for

23 years 8 months

Instead of resource lag, please consider the resource curve. I create one for concrete - 0% to whole period except the last one. So the curve is "flat" except the last day.



So no actual quantity until the concrete day and same day for the Actual Finish of this activity.