PROJECTS WITH HOURLY TIMESCALE

Member for

24 years 1 month

Thanks Philip, You are right! I did not know that feature is available nowadays.



Regards,

Daniel

Member for

21 years

P3 can schedule in hours. When you start a new project, select hours next to planning unit.

Member for

24 years 1 month

There is a P3 version called "Finest Hour", This software allows you to schedule in Hours. I dont know if it is still available in the market. We used this software when it was still in DOS version. You can always inquire with Primavera.



Regards,

Daniel

Member for

20 years 11 months

Hi, Kris.

It’s not too much difference when you’re working with hour based calendar. You’ll find an extra scale in calendar definition form - hours. Of course now you’ll deal with working time for each day. By default P3 assumes that each working day is starting at 12:00 AM and ending at 11:59 PM. So you’ve to change this extra night shift standard calendar according to you scenario.

Best regards,

Andrew