Planning, Scheduling & Programming Discussion Member for 20 years 5 months Member for 20 years 5 months Submitted by Peter Holroyd on Sat, 2023-02-18 13:09 Permalink John,corporate directive- all John, corporate directive - all schedules should be 90% of contract time with TRA added! - Float should be spread evenly along the EPC path. Peter Log in or register to post comments
Member for 20 years 5 months Member for 20 years 5 months Submitted by Peter Holroyd on Sat, 2023-02-18 13:09 Permalink John,corporate directive- all John, corporate directive - all schedules should be 90% of contract time with TRA added! - Float should be spread evenly along the EPC path. Peter
Member for
20 years 5 monthsJohn,corporate directive- all
John,
corporate directive
- all schedules should be 90% of contract time with TRA added!
- Float should be spread evenly along the EPC path.
Peter