Activity duration is a function of assigned resources and their production rates.
Individual resource productivity is not the same as team productivity. The production rate for a crew of 2 steel fixers is usually twice the production rate for a crew of 1 steel fixer but it can be other factor.
The production average production rate is a function of crew production rate, crew assgment and crew work hours.
If using Spider Project we can assign production rate at the activity level or at individual resources. Spider Project Production Type activityes, Multiresources as a Skill and resource leveling will automatically select best available crew and adjust activity durations per crew production rate.
Member for
21 years 8 months(No subject)
Member for
21 years 8 monthsActivity duration is a
Good Luck.