  • Activity duration is a function of assigned resources and their production rates.
  • Individual resource productivity is not the same as team productivity. The production rate for a crew of 2 steel fixers is usually twice the production rate for a crew of 1 steel fixer but it can be other factor.
  • The production average production rate is a function of crew production rate, crew assgment and crew work hours.
  • If using Spider Project we can assign production rate at the activity level or at individual resources. Spider Project Production Type activityes, Multiresources as a Skill and resource leveling will automatically select best available crew and adjust activity durations per crew production rate.