I have check both the late and early exertnal finishs but the coloumns are blank.
The scheduling options is not ticked but i dont beleive the schedule will be affected by these links.
from what i understand my collegue has copied the WBS so all my activities have successor to their project but that is it, so they are all open ends. It is just very confusing going to the successor box and seeing 15 links in that are of no use.
i can go through and delete but i have 2500 activities in my schedule to check.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Fri, 2016-10-14 13:45
Member for
19 years 5 monthsThanks for the post back. I
Thanks for the post back.
I have check both the late and early exertnal finishs but the coloumns are blank.
The scheduling options is not ticked but i dont beleive the schedule will be affected by these links.
from what i understand my collegue has copied the WBS so all my activities have successor to their project but that is it, so they are all open ends. It is just very confusing going to the successor box and seeing 15 links in that are of no use.
i can go through and delete but i have 2500 activities in my schedule to check.
Member for
16 years 3 monthsyou have several
you have several options
Option 1 go to tools schedule
select options
then select ignore relationships to and from other projects
option #2
filter for all activities
right click columns
expand the dates availability on the left and choose
External Early Start and also choose External Early Finish
now in the External Early Start column Blank out the dated
now do a fill down a
Now do the same thing for the External Early Finish Column
Option #3
go to tools
global change
New (on the right)
Where (leave this line blank)
then
External Early Start = (leave the rest of the line blank)
and
External Early Finish = (leave the rest of the line blank)
then on the right select change
then commit changes
what ever option that you choose make sure to run the schedule calculations after you run your option