Planning, Scheduling & Programming Discussion Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Fri, 2016-10-14 05:36 Permalink Hi JamesIt is the same method Hi James It is the same method as described in an Impacted as Planned delay analysis method. 1. Calculate the duration of the compensation event. 2. Set this into a Sub Chart. 3. Link to the affected task(s). 4. Hit F9 and wait for the howls of protest from the CA. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Fri, 2016-10-14 05:36 Permalink Hi JamesIt is the same method Hi James It is the same method as described in an Impacted as Planned delay analysis method. 1. Calculate the duration of the compensation event. 2. Set this into a Sub Chart. 3. Link to the affected task(s). 4. Hit F9 and wait for the howls of protest from the CA. Best regards Mike Testro
Member for
19 years 10 monthsHi JamesIt is the same method
Hi James
It is the same method as described in an Impacted as Planned delay analysis method.
1. Calculate the duration of the compensation event.
2. Set this into a Sub Chart.
3. Link to the affected task(s).
4. Hit F9 and wait for the howls of protest from the CA.
Best regards