Compensation Events

Member for

19 years 10 months

Hi James

It is the same method as described in an Impacted as Planned delay analysis method.

1. Calculate the duration of the compensation event.

2. Set this into a Sub Chart.

3. Link to the affected task(s).

4. Hit F9 and wait for the howls of protest from the CA.

Best regards