Report: Current Week Activities

Member for

15 years 11 months

Hi,

Suggests to assign activity codes to use for grouping and filter using Current Day+7d

 

Member for

9 years 5 months

Hi Stefano,

You can do this by filtering for the dates. The only thing to be wary of is if you filter for work in the fourth week of the month for example, but the activities for the first three did not go as planned and are still open.

Member for

9 years 5 months

Hi Stefano,

You can do this by filtering for the dates. The only thing to be wary of is if you filter for work in the fourth week of the month for example, but the activities for the first three did not go as planned and are still open.

Member for

24 years 9 months

Stefano, it depends on the software that you use.

In Spider Project you just select the period and that's all. It is standard function.