Leveling issues, "pinning activities in place"

Member for

9 years 9 months

Hamza,

The functioality of Resource Levelling in P6 is incomplete.

However if you use 'Start on or after' and 'Finish on or before' constraints to pin activities, and when levelling you should, in levelling option, tick the option 'level resources only within total float' you might get close to the result you want