How to edit gray boxes in Resource Usage Spreadsheet

Member for

3 years 3 months

It Worked!!

Great. Thanks for your help.

The issue was duration type. I changed it from "Fixed Units"to "Fixed Duration & Units"

Member for

3 years 3 months

It Worked!!

Great. Thanks for your help.

The issue was duration type. I changed it from "Fixed Units"to "Fixed Duration & Units"

Member for

9 years 9 months

Check out page five of the PDF document 'Using a holiday plan rather than calendar exceptions' that you will find on:

 

www.p6david.uk/tipnew

 

Currently the above page not behaving perfectly on Firefox, but fine on Edge