Hmm. 'Bleed together for resources' - this sounds a bit like a query about all projects sharing the same pool of resources. Which is correct, and almost the whole point of an enterprise-wide project management system. You can partition the resource dictionary such that you can emulate project-specific resources.
If, on import, you chose 'use existing' then the project might not match the original exported project, calendar details, resource availability etc.
Member for
9 years 9 monthsHmm. 'Bleed together for
Hmm. 'Bleed together for resources' - this sounds a bit like a query about all projects sharing the same pool of resources. Which is correct, and almost the whole point of an enterprise-wide project management system. You can partition the resource dictionary such that you can emulate project-specific resources.