Oracle Primavera - PM6 Member for 13 years 4 months Member for 13 years 5 months Submitted by rodneyoz on Tue, 2022-11-08 00:11 Permalink Hey John, Check your import Hey John, Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed? Member for 13 years 4 months Member for 13 years 5 months Submitted by rodneyoz on Tue, 2022-11-08 00:10 Permalink Hey John, Check your import Hey John, Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed? Member for 13 years 4 months Member for 13 years 5 months Submitted by rodneyoz on Tue, 2022-11-08 00:10 Permalink Hey John, Check your import Hey John, Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed? Member for 20 years 6 months Member for 20 years 7 months Submitted by Santosh Bhat on Wed, 2022-11-02 12:28 Permalink John,WBS has to be imported, John, WBS has to be imported, or else all activities are by default dropped into the very top level node. Log in or register to post comments
Member for 13 years 4 months Member for 13 years 5 months Submitted by rodneyoz on Tue, 2022-11-08 00:11 Permalink Hey John, Check your import Hey John, Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?
Member for 13 years 4 months Member for 13 years 5 months Submitted by rodneyoz on Tue, 2022-11-08 00:10 Permalink Hey John, Check your import Hey John, Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?
Member for 13 years 4 months Member for 13 years 5 months Submitted by rodneyoz on Tue, 2022-11-08 00:10 Permalink Hey John, Check your import Hey John, Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?
Member for 20 years 6 months Member for 20 years 7 months Submitted by Santosh Bhat on Wed, 2022-11-02 12:28 Permalink John,WBS has to be imported, John, WBS has to be imported, or else all activities are by default dropped into the very top level node.
Member for
13 years 4 monthsHey John, Check your import
Hey John,
Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?
Member for
13 years 4 monthsHey John, Check your import
Hey John,
Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?
Member for
13 years 4 monthsHey John, Check your import
Hey John,
Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?
Member for
20 years 6 monthsJohn,WBS has to be imported,
John,
WBS has to be imported, or else all activities are by default dropped into the very top level node.