Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2022-04-18 21:19 Permalink its a 2 step process you can its a 2 step process you can compare up to 3 baselines 1st select project maintain basleine then select assign baseline do this for up to 3 baselines Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Mon, 2022-04-18 14:27 Permalink Hi Rami,That is not possible Hi Rami, That is not possible because the database only accept one at a time maintaining baseline and the same with assigning Baseline. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2022-04-18 21:19 Permalink its a 2 step process you can its a 2 step process you can compare up to 3 baselines 1st select project maintain basleine then select assign baseline do this for up to 3 baselines
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Mon, 2022-04-18 14:27 Permalink Hi Rami,That is not possible Hi Rami, That is not possible because the database only accept one at a time maintaining baseline and the same with assigning Baseline.
Member for
16 years 3 monthsits a 2 step process you can
its a 2 step process you can compare up to 3 baselines
1st select project maintain basleine then select assign baseline
do this for up to 3 baselines
Member for
19 yearsHi Rami,That is not possible
Hi Rami,
That is not possible because the database only accept one at a time maintaining baseline and the same with assigning Baseline.