My response was "In OPP v3.1 there is an option to allocate an EVT to each activity HOWEVER OPP does not actually use that information. For example, if you added an EVT of 0-100 it would let you enter in 50%."
I was referring to how open plan works not how Earned Value works. In OPPv3.1 you can assigned an EVT to each activity HOWEVER it doesnt use that information THEREFORE a user CAN enter in 50% on an activity which was meant to be 0-100 and it WILL calculate the EV at 50% of BAC.
Frank is correct. Also, if you are using progress calculations to compute Physical Percent complete you must check the option to Base Physical Percent Complete on EVT.
Member for
24 years 6 months
Member for24 years6 months
Submitted by Frank Borcherdt on Fri, 2005-05-27 19:13
0-100 means you do not earn any value until you reach the 100% mark....you can still be 50% complete and you will find the earned value reported is $0 and will remain so until you reach 100% complete.
HTH
Member for
21 years 9 months
Member for21 years10 months
Submitted by Joanne Foster on Fri, 2005-05-27 06:17
In OPP v3.1 there is an option to allocate an EVT to each activity HOWEVER OPP does not actually use that information. For example, if you added an EVT of 0-100 it would let you enter in 50%.
Member for
24 years 6 monthsRE: Earned Value at activity level
J,
Were using OPP with Cobra and all EV reports came from Cobra so never noticed....no longer using either.
Member for
21 years 9 monthsRE: Earned Value at activity level
John/Frank
My response was "In OPP v3.1 there is an option to allocate an EVT to each activity HOWEVER OPP does not actually use that information. For example, if you added an EVT of 0-100 it would let you enter in 50%."
I was referring to how open plan works not how Earned Value works. In OPPv3.1 you can assigned an EVT to each activity HOWEVER it doesnt use that information THEREFORE a user CAN enter in 50% on an activity which was meant to be 0-100 and it WILL calculate the EV at 50% of BAC.
J
Member for
20 years 5 monthsRE: Earned Value at activity level
Frank is correct. Also, if you are using progress calculations to compute Physical Percent complete you must check the option to Base Physical Percent Complete on EVT.
Member for
24 years 6 monthsRE: Earned Value at activity level
J,
0-100 means you do not earn any value until you reach the 100% mark....you can still be 50% complete and you will find the earned value reported is $0 and will remain so until you reach 100% complete.
HTH
Member for
21 years 9 monthsRE: Earned Value at activity level
In OPP v3.1 there is an option to allocate an EVT to each activity HOWEVER OPP does not actually use that information. For example, if you added an EVT of 0-100 it would let you enter in 50%.
J