how can define a task that last from start of project to finish of project??

Member for

18 years 11 months

The paste-links seem a bit more robust in newer versions than they were in 2003, but it's still a patchwork approach.  Past experience mostly cured me of my desire for hammocks in MSP.  Now on the few occasions I can't do without, I use alternate methods that don't give me a big headache....

http://www.boyleprojectconsulting.com/TomsBlog/2017/09/26/an-alternate-approach-to-hammocks-in-microsoft-project/

Member for

7 years 11 months

I agree with Mike. This sounds like the best solution. I am still learning to use MSP and this forum will definitely help. 

Member for

22 years 9 months

Hello Gary,

no, there is no cleaner / clever way in MSP 2007 / 2010 to build a hammock task; the way you've described is the only wy to do that

Alexandre

Member for

16 years 7 months

1) Set up & logically link normal start & finish milestones for the start and finish of your project.

2) Copy the Start field of your start milestone, then right click on the start field of your "level of effort" task, choose paste special > paste link

3) Do the same with the finish date from your finish milestone

4) Put something in the notes column explaining what you did, as the start & finish milestones won't register as predecessors of the "level of effort" task

 

 

This is For MSP 2003. There may be a cleaner way in later versions.

 

Member for

19 years 10 months

Hi Shima

Create a summary bar over all the tasks and label it your task long activity.

Best regards

Mike Testro