Asta Powerproject Member for 6 years 1 month Member for 6 years 1 month Submitted by yarkinbilgic on Tue, 2020-07-14 13:12 Permalink Thank you for your reply, I Thank you for your reply, I couldnt reflect the changes to the summary headings. Could you please show me steps if you dont mind? Also, for the time to go column, do you have any idea how to insert it? Thank you, Kind regards, Yarkin Member for 13 years 9 months Member for 13 years 10 months Submitted by Ben Taunt on Mon, 2020-07-13 10:22 Permalink Hi Yarkin,It looks like your Hi Yarkin, It looks like your view has a sort on it. If so, the setting to hide column details on a sort is within the Sort/Group Properties: [[wysiwyg_imageupload:7468:]] You will need to chose "Sub-heading with only name column" to get the desired view. Thanks, Ben @ Powerproject Log in or register to post comments
Member for 6 years 1 month Member for 6 years 1 month Submitted by yarkinbilgic on Tue, 2020-07-14 13:12 Permalink Thank you for your reply, I Thank you for your reply, I couldnt reflect the changes to the summary headings. Could you please show me steps if you dont mind? Also, for the time to go column, do you have any idea how to insert it? Thank you, Kind regards, Yarkin
Member for 13 years 9 months Member for 13 years 10 months Submitted by Ben Taunt on Mon, 2020-07-13 10:22 Permalink Hi Yarkin,It looks like your Hi Yarkin, It looks like your view has a sort on it. If so, the setting to hide column details on a sort is within the Sort/Group Properties: [[wysiwyg_imageupload:7468:]] You will need to chose "Sub-heading with only name column" to get the desired view. Thanks, Ben @ Powerproject
Member for
6 years 1 monthThank you for your reply, I
Thank you for your reply, I couldnt reflect the changes to the summary headings. Could you please show me steps if you dont mind? Also, for the time to go column, do you have any idea how to insert it?
Thank you,
Kind regards,
Yarkin
Member for
13 years 9 monthsHi Yarkin,It looks like your
Hi Yarkin,
It looks like your view has a sort on it. If so, the setting to hide column details on a sort is within the Sort/Group Properties:
[[wysiwyg_imageupload:7468:]]
You will need to chose "Sub-heading with only name column" to get the desired view.
Thanks,
Ben @ Powerproject