In the Date Zone Properties (right-click within the Date Zone > Properties), the line currently representing your week numbering will likely state Type = "Elapsed Units", Time Unit = "Weeks". If you change Elapsed Units to instead be "Working Units", it will reflect your folding calendar's exceptions. You should then see the change you want in your date zone.
Member for
8 years 7 monthsBrilliant, that worked thanks
Brilliant, that worked thanks Ben!
Member for
13 years 9 monthsHi Alex,In the Date Zone
Hi Alex,
In the Date Zone Properties (right-click within the Date Zone > Properties), the line currently representing your week numbering will likely state Type = "Elapsed Units", Time Unit = "Weeks". If you change Elapsed Units to instead be "Working Units", it will reflect your folding calendar's exceptions. You should then see the change you want in your date zone.
[[wysiwyg_imageupload:7064:]]
Best wishes,
Ben @ Powerproject