Asta Powerproject Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2018-09-05 16:49 Permalink Hi PaulWhy go to such Hi Paul Why go to such bother. Set your reschedule window to block out completed tasks. Or show the Percent complete Nr 0% to 100% and that will show the data you want. Best regards Mike Testro. Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2018-09-05 16:49 Permalink Hi PaulWhy go to such Hi Paul Why go to such bother. Set your reschedule window to block out completed tasks. Or show the Percent complete Nr 0% to 100% and that will show the data you want. Best regards Mike Testro.
Member for
19 years 10 monthsHi PaulWhy go to such
Hi Paul
Why go to such bother.
Set your reschedule window to block out completed tasks.
Or show the Percent complete Nr 0% to 100% and that will show the data you want.
Best regards
Mike Testro.