Asta Powerproject Member for 8 years 4 months Member for 8 years 4 months Submitted by Danz on Wed, 2018-01-31 17:01 Permalink while a constraint would while a constraint would work, i would suggest adding an activity with the necessary logic for the 2 week lag such as "gas utility availabe to peform hook-up' Member for 7 years 9 months Member for 7 years 9 months Submitted by jamesbb on Wed, 2018-01-31 11:04 Permalink Thansk Mike :) Worked a Thansk Mike :) Worked a treat, just what I was after! Member for 7 years 9 months Member for 7 years 9 months Submitted by jamesbb on Wed, 2018-01-31 11:04 Permalink Thansk Mike :) Worked a Thansk Mike :) Worked a treat, just what I was after! Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Tue, 2018-01-30 12:44 Permalink Hi James Welcome to Planning Hi James Welcome to Planning Plant The easiest way is to put a "Must Start On or After" constraint flag on the task. Be careful of these because Powerproject does not work on negative float. Best regards Mike T. Log in or register to post comments
Member for 8 years 4 months Member for 8 years 4 months Submitted by Danz on Wed, 2018-01-31 17:01 Permalink while a constraint would while a constraint would work, i would suggest adding an activity with the necessary logic for the 2 week lag such as "gas utility availabe to peform hook-up'
Member for 7 years 9 months Member for 7 years 9 months Submitted by jamesbb on Wed, 2018-01-31 11:04 Permalink Thansk Mike :) Worked a Thansk Mike :) Worked a treat, just what I was after!
Member for 7 years 9 months Member for 7 years 9 months Submitted by jamesbb on Wed, 2018-01-31 11:04 Permalink Thansk Mike :) Worked a Thansk Mike :) Worked a treat, just what I was after!
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Tue, 2018-01-30 12:44 Permalink Hi James Welcome to Planning Hi James Welcome to Planning Plant The easiest way is to put a "Must Start On or After" constraint flag on the task. Be careful of these because Powerproject does not work on negative float. Best regards Mike T.
Member for
8 years 4 monthswhile a constraint would
while a constraint would work, i would suggest adding an activity with the necessary logic for the 2 week lag such as "gas utility availabe to peform hook-up'
Member for
7 years 9 monthsThansk Mike :) Worked a
Thansk Mike :) Worked a treat, just what I was after!
Member for
7 years 9 monthsThansk Mike :) Worked a
Thansk Mike :) Worked a treat, just what I was after!
Member for
19 years 10 monthsHi James Welcome to Planning
Hi James Welcome to Planning Plant
The easiest way is to put a "Must Start On or After" constraint flag on the task.
Be careful of these because Powerproject does not work on negative float.
Best regards
Mike T.