Asta Powerproject Member for 7 years 9 months Member for 7 years 9 months Submitted by Mackin on Thu, 2018-01-25 21:04 Permalink Thanks Mike. I did try the Thanks Mike. I did try the copy and paste but maybe I wasn't doing it correctly. I was able to copy a task, and paste it into the new schedule and it carried the calendar with it. Thanks again! Jeff Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2018-01-25 17:24 Permalink Hi JeffHighlight and copy the Hi Jeff Highlight and copy the calendar you want. Go to the new project and copy the calendar. If the calendar wizard pops up then disable it first. Alternatively copy a single task and copy it into the new projoject and it should bring all the other objects with it for you to retain or de select. Best regards Mike T. Log in or register to post comments
Member for 7 years 9 months Member for 7 years 9 months Submitted by Mackin on Thu, 2018-01-25 21:04 Permalink Thanks Mike. I did try the Thanks Mike. I did try the copy and paste but maybe I wasn't doing it correctly. I was able to copy a task, and paste it into the new schedule and it carried the calendar with it. Thanks again! Jeff
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2018-01-25 17:24 Permalink Hi JeffHighlight and copy the Hi Jeff Highlight and copy the calendar you want. Go to the new project and copy the calendar. If the calendar wizard pops up then disable it first. Alternatively copy a single task and copy it into the new projoject and it should bring all the other objects with it for you to retain or de select. Best regards Mike T.
Member for
7 years 9 monthsThanks Mike. I did try the
Thanks Mike. I did try the copy and paste but maybe I wasn't doing it correctly. I was able to copy a task, and paste it into the new schedule and it carried the calendar with it.
Thanks again!
Jeff
Member for
19 years 10 monthsHi JeffHighlight and copy the
Hi Jeff
Highlight and copy the calendar you want.
Go to the new project and copy the calendar.
If the calendar wizard pops up then disable it first.
Alternatively copy a single task and copy it into the new projoject and it should bring all the other objects with it for you to retain or de select.
Best regards
Mike T.