Asta Powerproject Member for 20 years 6 months Member for 20 years 6 months Submitted by Ben Jewell on Wed, 2013-11-27 11:19 Permalink Thanks Mike.I was hoping to Thanks Mike. I was hoping to avoid using hammocks but looks like that will be the quickest and easiest way to go. Ben Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2013-11-27 11:01 Permalink Hi BenSet up a hammock task Hi Ben Set up a hammock task for steelwork and add all the relevant steelwork tasks under the hammock. Then put the hammock under a summary bar and add the steelwork costs to the summary. Best regards Mike Testro Log in or register to post comments
Member for 20 years 6 months Member for 20 years 6 months Submitted by Ben Jewell on Wed, 2013-11-27 11:19 Permalink Thanks Mike.I was hoping to Thanks Mike. I was hoping to avoid using hammocks but looks like that will be the quickest and easiest way to go. Ben
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2013-11-27 11:01 Permalink Hi BenSet up a hammock task Hi Ben Set up a hammock task for steelwork and add all the relevant steelwork tasks under the hammock. Then put the hammock under a summary bar and add the steelwork costs to the summary. Best regards Mike Testro
Member for
20 years 6 monthsThanks Mike.I was hoping to
Thanks Mike.
I was hoping to avoid using hammocks but looks like that will be the quickest and easiest way to go.
Ben
Member for
19 years 10 monthsHi BenSet up a hammock task
Hi Ben
Set up a hammock task for steelwork and add all the relevant steelwork tasks under the hammock.
Then put the hammock under a summary bar and add the steelwork costs to the summary.
Best regards
Mike Testro