Asta Powerproject Member for 20 years 6 months Member for 20 years 6 months Submitted by Ben Jewell on Thu, 2013-10-31 15:37 Permalink Hi Mike, Thanks very much for Hi Mike, Thanks very much for that, I'll give it a shot in the next couple of days once I have the Excel work finalised. I had a feeling, based on my previous experiences with Asta, that it would be possible. I just need to get used to a slightly different work flow! Ben Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2013-10-30 18:25 Permalink Hi BenI gather from your Hi Ben I gather from your query that you are more used to working in a P6 environment. Asta works differently You can copy paste any sort of data from a spreadsheet to an Asta programme EXCEPT logic links and summary bars.. So if you copy and paste the tasks and durations first then set up the code libraries you can copy paste these values from the spreadsheet. Set up the programme columns first then copy paste afterwards. You will then be faced with the laborius task of logic links and summaries but these may not be necessary in a template. Make sure that the Tools > Reschedule > dialogue sets the tasks with no links to Leave as Drawn - otherwise thay will all drop back to the start date. Hope that helps Mike Testro Log in or register to post comments
Member for 20 years 6 months Member for 20 years 6 months Submitted by Ben Jewell on Thu, 2013-10-31 15:37 Permalink Hi Mike, Thanks very much for Hi Mike, Thanks very much for that, I'll give it a shot in the next couple of days once I have the Excel work finalised. I had a feeling, based on my previous experiences with Asta, that it would be possible. I just need to get used to a slightly different work flow! Ben
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2013-10-30 18:25 Permalink Hi BenI gather from your Hi Ben I gather from your query that you are more used to working in a P6 environment. Asta works differently You can copy paste any sort of data from a spreadsheet to an Asta programme EXCEPT logic links and summary bars.. So if you copy and paste the tasks and durations first then set up the code libraries you can copy paste these values from the spreadsheet. Set up the programme columns first then copy paste afterwards. You will then be faced with the laborius task of logic links and summaries but these may not be necessary in a template. Make sure that the Tools > Reschedule > dialogue sets the tasks with no links to Leave as Drawn - otherwise thay will all drop back to the start date. Hope that helps Mike Testro
Member for
20 years 6 monthsHi Mike, Thanks very much for
Hi Mike,
Thanks very much for that, I'll give it a shot in the next couple of days once I have the Excel work finalised.
I had a feeling, based on my previous experiences with Asta, that it would be possible. I just need to get used to a slightly different work flow!
Ben
Member for
19 years 10 monthsHi BenI gather from your
Hi Ben
I gather from your query that you are more used to working in a P6 environment.
Asta works differently
You can copy paste any sort of data from a spreadsheet to an Asta programme EXCEPT logic links and summary bars..
So if you copy and paste the tasks and durations first then set up the code libraries you can copy paste these values from the spreadsheet.
Set up the programme columns first then copy paste afterwards.
You will then be faced with the laborius task of logic links and summaries but these may not be necessary in a template.
Make sure that the Tools > Reschedule > dialogue sets the tasks with no links to Leave as Drawn - otherwise thay will all drop back to the start date.
Hope that helps
Mike Testro