Changing format in Text Annotations

Member for

19 years 10 months

Hi Craig

I have just replicated your situation and the 2 decimal default is fixed - I could find no way to edit it.

You can put a text % symbol after the decimals.

Put it on the Asta Wish List for the next edition.

Best regards

Mike Testro

Member for

19 years 1 month

Hello Mike,

I understand how to change percent to show % in columns, however in this case I am using annotations in the chart area and I have set them to show the percentages.

The annotations do not change when you change the columns, they remain the same with two decimal places. It's the annotations I am unable to change formating of not the actual percentage column.

Cheers,

Craig Adams

Member for

19 years 10 months

Hi Craig

High Light the coloumn

Right Click and select Format Cells

Select Percent - select 0 decimals

Click OK and you get the percent sign.

Best regards

Mike Testro