The start and end date columns look at the project data when you first set them up. To point them at a baseline right click on the heading of the column and select Table Definition. Make sure the column you want to amend is selected in the left hand window. In the right hand window the Detail tab will show Live, click into here and select the baseline. This should be repeated for any column that you want to show baseline data.
Member for
15 years 5 monthsThe start and end date
The start and end date columns look at the project data when you first set them up. To point them at a baseline right click on the heading of the column and select Table Definition. Make sure the column you want to amend is selected in the left hand window. In the right hand window the Detail tab will show Live, click into here and select the baseline. This should be repeated for any column that you want to show baseline data.
Hope this helps
Chris
Member for
19 years 10 monthsHi Lee Use the baseline
Hi Lee
Use the baseline option to show the bars in there own lines or set up start and end date columns that rela\te to the baseline.
Best regards
Mike Testro