Asta Powerproject Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sat, 2010-05-29 02:49 Permalink RE: Powerproject v10.3 Hi Robert Asta v 10 has a sort function that is on a hair trigger. You may have inadvertantly sorted the tasks into date order or similar by double left clicking the column head. Go to view> Sort> and tick Natural Order and it should come back into line. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sat, 2010-05-29 02:49 Permalink RE: Powerproject v10.3 Hi Robert Asta v 10 has a sort function that is on a hair trigger. You may have inadvertantly sorted the tasks into date order or similar by double left clicking the column head. Go to view> Sort> and tick Natural Order and it should come back into line. Best regards Mike Testro
Member for
19 years 10 monthsRE: Powerproject v10.3
Hi Robert
Asta v 10 has a sort function that is on a hair trigger.
You may have inadvertantly sorted the tasks into date order or similar by double left clicking the column head.
Go to view> Sort> and tick Natural Order and it should come back into line.
Best regards
Mike Testro