Asta Powerproject Member for 22 years 5 months Member for 22 years 5 months Submitted by David Uttley on Fri, 2009-09-04 03:39 Permalink RE: Converting ASTA power Project File to P3 Nokhez - if you want some local support, feel free to contact us at Solid Support 02 9743 4666. We run a helpdesk for Asta Power Project users who have maintenance agrrements with us. help@solidsupport.com.au Good to see your company (TBH) are trialing / experimenting with the software. Member for 18 years 4 months Member for 18 years 5 months Submitted by Nokhez Akhtar on Mon, 2009-08-17 20:40 Permalink RE: Converting ASTA power Project File to P3 Thanks Mike I got it. Regards Nokhez Akhtar Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2009-08-17 10:27 Permalink RE: Converting ASTA power Project File to P3 Hi Nokhez. I am assuming that you have PowerProject v 10 and P3 on the same computer and you are using the standard Icons in PowerProject. The error note indicates that you are using an invalid calendar or workpattern that is not used on P3. I suggest you review your calendars and apply a standard 8 hr day 5 day week on PowerProject tasks before trying to convert. Best regards Mike Testro Log in or register to post comments
Member for 22 years 5 months Member for 22 years 5 months Submitted by David Uttley on Fri, 2009-09-04 03:39 Permalink RE: Converting ASTA power Project File to P3 Nokhez - if you want some local support, feel free to contact us at Solid Support 02 9743 4666. We run a helpdesk for Asta Power Project users who have maintenance agrrements with us. help@solidsupport.com.au Good to see your company (TBH) are trialing / experimenting with the software.
Member for 18 years 4 months Member for 18 years 5 months Submitted by Nokhez Akhtar on Mon, 2009-08-17 20:40 Permalink RE: Converting ASTA power Project File to P3 Thanks Mike I got it. Regards Nokhez Akhtar
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2009-08-17 10:27 Permalink RE: Converting ASTA power Project File to P3 Hi Nokhez. I am assuming that you have PowerProject v 10 and P3 on the same computer and you are using the standard Icons in PowerProject. The error note indicates that you are using an invalid calendar or workpattern that is not used on P3. I suggest you review your calendars and apply a standard 8 hr day 5 day week on PowerProject tasks before trying to convert. Best regards Mike Testro
Member for
22 years 5 monthsRE: Converting ASTA power Project File to P3
Nokhez - if you want some local support, feel free to contact us at Solid Support 02 9743 4666.
We run a helpdesk for Asta Power Project users who have maintenance agrrements with us.
help@solidsupport.com.au
Good to see your company (TBH) are trialing / experimenting with the software.
Member for
18 years 4 monthsRE: Converting ASTA power Project File to P3
Thanks Mike I got it.
Regards
Nokhez Akhtar
Member for
19 years 10 monthsRE: Converting ASTA power Project File to P3
Hi Nokhez.
I am assuming that you have PowerProject v 10 and P3 on the same computer and you are using the standard Icons in PowerProject.
The error note indicates that you are using an invalid calendar or workpattern that is not used on P3.
I suggest you review your calendars and apply a standard 8 hr day 5 day week on PowerProject tasks before trying to convert.
Best regards
Mike Testro