Asta Powerproject Member for 19 years Member for 19 years 1 month Submitted by Laurie Willis on Wed, 2007-11-21 05:44 Permalink RE: Formatting the weekend display Alexandre thanks for your reply. In the end the customer decided they like the bars, so I didnt have a chance to try out your suggestion. But thank you for your help. Member for 22 years 9 months Member for 22 years 10 months Submitted by Alexandre Faul… on Tue, 2007-11-06 13:38 Permalink RE: Formatting the weekend display Laurie, I am using PP8; I would check Work Pattern in the Library: The saturdays and sundays your wp should be set-up as follows in the 8hr/day, 5d/w pattern: Non-working: 00:00 - 09:00 (or 08:00) Week-end: 08:00 (or 09:00) - 17:00 Non-working: 17:00 - 00:00 and as follows in the 8hr/day, 7d/w pattern: Non-working: 00:00 - 09:00 (or 08:00) Working: 08:00 (or 09:00) - 12:00 Non-working: 12:00 - 13:00 Working: 13:00 - 17:00 Non-working: 17:00 - 00:00 I presume the wrong display comes from there. Hope this helps Alexandre Log in or register to post comments
Member for 19 years Member for 19 years 1 month Submitted by Laurie Willis on Wed, 2007-11-21 05:44 Permalink RE: Formatting the weekend display Alexandre thanks for your reply. In the end the customer decided they like the bars, so I didnt have a chance to try out your suggestion. But thank you for your help.
Member for 22 years 9 months Member for 22 years 10 months Submitted by Alexandre Faul… on Tue, 2007-11-06 13:38 Permalink RE: Formatting the weekend display Laurie, I am using PP8; I would check Work Pattern in the Library: The saturdays and sundays your wp should be set-up as follows in the 8hr/day, 5d/w pattern: Non-working: 00:00 - 09:00 (or 08:00) Week-end: 08:00 (or 09:00) - 17:00 Non-working: 17:00 - 00:00 and as follows in the 8hr/day, 7d/w pattern: Non-working: 00:00 - 09:00 (or 08:00) Working: 08:00 (or 09:00) - 12:00 Non-working: 12:00 - 13:00 Working: 13:00 - 17:00 Non-working: 17:00 - 00:00 I presume the wrong display comes from there. Hope this helps Alexandre
Member for
19 yearsRE: Formatting the weekend display
Alexandre thanks for your reply. In the end the customer decided they like the bars, so I didnt have a chance to try out your suggestion.
But thank you for your help.
Member for
22 years 9 monthsRE: Formatting the weekend display
Laurie,
I am using PP8; I would check Work Pattern in the Library: The saturdays and sundays your wp should be set-up as follows in the 8hr/day, 5d/w pattern:
Non-working: 00:00 - 09:00 (or 08:00)
Week-end: 08:00 (or 09:00) - 17:00
Non-working: 17:00 - 00:00
and as follows in the 8hr/day, 7d/w pattern:
Non-working: 00:00 - 09:00 (or 08:00)
Working: 08:00 (or 09:00) - 12:00
Non-working: 12:00 - 13:00
Working: 13:00 - 17:00
Non-working: 17:00 - 00:00
I presume the wrong display comes from there.
Hope this helps
Alexandre