Time Location software

Member for

20 years 3 months

Hi,



I’m working with a software called Tilos from Asta Development. It seems to be the same program as Linea Interactive of primavera, which is not the same as Linea was before.

It is possible to get a trial-version.



I think a better description is "Time - Chainage Diagram" - software.



Regards



Hannes

Member for

22 years 9 months

Vladimir,

yes, you can call that a 3d gantt chart; in French, we used to all that kind of planning "planning chemin de fer" (railway planning); easy to undersatnd why.

All the best

Member for

24 years 9 months

So it is supported by Spider Project.

What is the difference between Time Location and Line of Balance presentations? We have different terminology and an amount of termins for the same presentation is confusing (time location, line of balance, time chainage).

In Spider Project this presentation is called Linear Diagram.

But why Gantt Chart? Do you mean 3D Gantt Charts?

Member for

22 years 9 months

Hi there,

time location software represents tasks on a gantt chart with the two dimensions time and location; it is very usefull for road construction, railways, ...

Astadev Germany has developped Tilos; there was an excellent tl software in France about 10 years ago, but I don’t see it today on the market.

Alexandre

Member for

24 years 9 months

Sanjay,

what do you mean by time location planning? Please clarify.