Asta Powerproject Member for 21 years 1 month Member for 21 years 1 month Submitted by Peter Roscoe on Thu, 2006-08-03 09:33 Permalink RE: Power project massive increase in file size Try a "save as" this usually compoacts the database. Member for 22 years 9 months Member for 22 years 10 months Submitted by Alexandre Faul… on Sat, 2006-01-14 05:23 Permalink RE: Power project massive increase in file size hello, have you worked heavily in the Code Library in between? It could explain the size growth, as everything is stored in the project file. Alexandre Log in or register to post comments
Member for 21 years 1 month Member for 21 years 1 month Submitted by Peter Roscoe on Thu, 2006-08-03 09:33 Permalink RE: Power project massive increase in file size Try a "save as" this usually compoacts the database.
Member for 22 years 9 months Member for 22 years 10 months Submitted by Alexandre Faul… on Sat, 2006-01-14 05:23 Permalink RE: Power project massive increase in file size hello, have you worked heavily in the Code Library in between? It could explain the size growth, as everything is stored in the project file. Alexandre
Member for
21 years 1 monthRE: Power project massive increase in file size
Try a "save as" this usually compoacts the database.
Member for
22 years 9 monthsRE: Power project massive increase in file size
hello,
have you worked heavily in the Code Library in between?
It could explain the size growth, as everything is stored in the project file.
Alexandre