I cannot see the image so I'm guessing in here. Can you check the Resources Sheet if no resources define or added because it has it's own calendar. Make sure you deleted all the resouces define in Resources Sheet even it is not assigned on task. Logic should not be a problem and shall exist. Another issue that you may encounter is the long file name of MS Project (MPP). This need to be shorten to P6 Project ID length define on P6 settings. WBS and Task Description shall not be more than 100 characters and No logic assign on WBS. Once all of these are clear, convert to MPX and try again if the error still exist.
Member for
16 years 3 monthsget this software
get this software xertransfer
it can go both ways you can even maps fields back and fourth
https://www.xertransfer.com/
Member for
7 years 5 monthsHi Santosh,Thank you - I have
Hi Santosh,
Thank you - I have recommended this already but the company I work for are reluctant to implement it.
Regards
Member for
7 years 5 monthsHi Santosh,Thank you - I have
Hi Santosh,
Thank you - I have recommended this already but the company I work for are reluctant to implement it.
Regards
Member for
20 years 6 monthsHave a look at the Utility
Have a look at the Utility called XerTransfer. The time and effort it saves you in coverting P6<>MSP is well worth the price paid for it.
Member for
19 yearsHi Jesse,I cannot see the
Hi Jesse,
I cannot see the image so I'm guessing in here. Can you check the Resources Sheet if no resources define or added because it has it's own calendar. Make sure you deleted all the resouces define in Resources Sheet even it is not assigned on task. Logic should not be a problem and shall exist. Another issue that you may encounter is the long file name of MS Project (MPP). This need to be shorten to P6 Project ID length define on P6 settings. WBS and Task Description shall not be more than 100 characters and No logic assign on WBS. Once all of these are clear, convert to MPX and try again if the error still exist.