you will need

1. a critical path report that shows the critical path of the project what items are the most urgent.

2. you will need a near term critical path report those things that are not critical but can become critical

3. You will need a 4 week look ahead report to see what is coming ahead of you.

4. You will need a long lead time item report so you can track this items

5. You will need a monthly narrative that reflects progress and any delays during the reporting period.

6. You will needan RFI log (request for information)

7. You will need a change order log

8. You will need a manpower forecast

9. You will need a cash flow curve

10. You will need a submittal log.