Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2022-04-18 21:28 Permalink you will need1. a critical you will need 1. a critical path report that shows the critical path of the project what items are the most urgent. 2. you will need a near term critical path report those things that are not critical but can become critical 3. You will need a 4 week look ahead report to see what is coming ahead of you. 4. You will need a long lead time item report so you can track this items 5. You will need a monthly narrative that reflects progress and any delays during the reporting period. 6. You will needan RFI log (request for information) 7. You will need a change order log 8. You will need a manpower forecast 9. You will need a cash flow curve 10. You will need a submittal log. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2022-04-18 21:28 Permalink you will need1. a critical you will need 1. a critical path report that shows the critical path of the project what items are the most urgent. 2. you will need a near term critical path report those things that are not critical but can become critical 3. You will need a 4 week look ahead report to see what is coming ahead of you. 4. You will need a long lead time item report so you can track this items 5. You will need a monthly narrative that reflects progress and any delays during the reporting period. 6. You will needan RFI log (request for information) 7. You will need a change order log 8. You will need a manpower forecast 9. You will need a cash flow curve 10. You will need a submittal log.
Member for
16 years 3 monthsyou will need1. a critical
you will need
1. a critical path report that shows the critical path of the project what items are the most urgent.
2. you will need a near term critical path report those things that are not critical but can become critical
3. You will need a 4 week look ahead report to see what is coming ahead of you.
4. You will need a long lead time item report so you can track this items
5. You will need a monthly narrative that reflects progress and any delays during the reporting period.
6. You will needan RFI log (request for information)
7. You will need a change order log
8. You will need a manpower forecast
9. You will need a cash flow curve
10. You will need a submittal log.