i understand what you are saying and i know the steps u already mentioned as i learned these during the semester. However my problem was not knowin what are the typical activities and its duration for such project because i havent been on site ever. Anws thanks for you reply though!
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2017-04-25 13:55
Member for
16 years 3 monthsdurations will come from
durations will come from quantities becasue duration = (quantity)(installation rate)/# of men to use
you have to know how much of something you have to install before know how long it will take
there are installation rates here at planning planet up top 9th tab from the left
Member for
8 years 6 monthshello ,i understand what you
hello ,
i understand what you are saying and i know the steps u already mentioned as i learned these during the semester. However my problem was not knowin what are the typical activities and its duration for such project because i havent been on site ever. Anws thanks for you reply though!
Member for
16 years 3 monthsis this our project or yours
is this our project or yours if you dont dig in and find out on your own you will never learn it.
So build it from the bottom of the ground up.
1. create your a wbs work break down structer
2. create you major activities
3. link activities together
4. assign durations
5. calculate the schedule
6. Review and revise