Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2017-04-13 13:55 Permalink glad I could help glad I could help Member for 9 years 6 months Member for 9 years 6 months Submitted by ndson89 on Wed, 2017-04-12 15:23 Permalink Hi Mr Zolfan,Your method Hi Mr Zolfan, Your method works!! thanks for the reply. Anderson Member for 16 years 10 months Member for 16 years 10 months Submitted by Amro Ahmed on Wed, 2017-04-12 07:52 Permalink Please also Make sure the Please also Make sure the following: - No filter has done in the update especially,(in progress activities) -in update , the option for thechnique computing pecent comletion is custom not 0/100 Good luck Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2017-04-10 15:15 Permalink assign the baseline then assign the baseline then select update baseline and select costs Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2017-04-13 13:55 Permalink glad I could help glad I could help
Member for 9 years 6 months Member for 9 years 6 months Submitted by ndson89 on Wed, 2017-04-12 15:23 Permalink Hi Mr Zolfan,Your method Hi Mr Zolfan, Your method works!! thanks for the reply. Anderson
Member for 16 years 10 months Member for 16 years 10 months Submitted by Amro Ahmed on Wed, 2017-04-12 07:52 Permalink Please also Make sure the Please also Make sure the following: - No filter has done in the update especially,(in progress activities) -in update , the option for thechnique computing pecent comletion is custom not 0/100 Good luck
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2017-04-10 15:15 Permalink assign the baseline then assign the baseline then select update baseline and select costs
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
9 years 6 monthsHi Mr Zolfan,Your method
Hi Mr Zolfan,
Your method works!! thanks for the reply.
Anderson
Member for
16 years 10 monthsPlease also Make sure the
Please also Make sure the following:
- No filter has done in the update especially,(in progress activities)
-in update , the option for thechnique computing pecent comletion is custom not 0/100
Good luck
Member for
16 years 3 monthsassign the baseline then
assign the baseline then select update baseline and select costs