Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2017-02-02 13:28 Permalink make sure that the activities make sure that the activities are assigned to the correct calendar Member for 16 years 10 months Member for 16 years 10 months Submitted by Kevin Rayner on Thu, 2017-02-02 12:56 Permalink Fixed now. the calendar had Fixed now. the calendar had been incorrectly amended. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2017-02-02 13:28 Permalink make sure that the activities make sure that the activities are assigned to the correct calendar
Member for 16 years 10 months Member for 16 years 10 months Submitted by Kevin Rayner on Thu, 2017-02-02 12:56 Permalink Fixed now. the calendar had Fixed now. the calendar had been incorrectly amended.
Member for
16 years 3 monthsmake sure that the activities
make sure that the activities are assigned to the correct calendar
Member for
16 years 10 monthsFixed now. the calendar had
Fixed now. the calendar had been incorrectly amended.