How do you create a schedule for a project with a gap period in the project contract

Member for

13 years 3 months

Greeting!

Both options suggested by mike are workable.

Member for

19 years 10 months

Hi Tylor

Two possibilities

Put the break period in the calendar as a non work duration.

Set up a dummy task with a 24/7 calendar and link it FS to the real tasks.

Best regards

Mike T.