I am doing an update for which one activity needs to finish on May 2nd and its saying remain finish cannot be earlier than remain start. Remain start is May 17 and I manually tried to change it but it's going back to May 17. What to do. Please help need it right away.
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Wed, 2012-06-06 14:31
Change the % complete type to physical. Then when you ammend the remaining duration, the % complete will not be adjusted.
Best practise is to use physical % complete by default for all activities, and only to use duration % complete when there is a direct relationship between % complete and remaining duration (which is rare).
Member for
10 years 1 monthHello Kitaki, How you found
Hello Kitaki,
How you found solution with your problem?
Regards/Cocoy
Member for
10 years 1 monthHello Kitaki, How you found
Hello Kitaki,
How you found solution with your problem?
Regards/Cocoy
Member for
9 years 8 monthsI am doing an update for
I am doing an update for which one activity needs to finish on May 2nd and its saying remain finish cannot be earlier than remain start. Remain start is May 17 and I manually tried to change it but it's going back to May 17. What to do. Please help need it right away.
Member for
16 years 7 monthsSridevi, Change the %
Sridevi,
Change the % complete type to physical. Then when you ammend the remaining duration, the % complete will not be adjusted.
Best practise is to use physical % complete by default for all activities, and only to use duration % complete when there is a direct relationship between % complete and remaining duration (which is rare).
Cheers,
G