Hello Kitaki,

 

How you found solution with your problem?

 

Regards/Cocoy

Member for

10 years 1 month

Hello Kitaki,

 

How you found solution with your problem?

 

Regards/Cocoy

Member for

9 years 8 months

I am doing an update for which one activity needs to finish on May 2nd and its saying remain finish cannot be earlier than remain start. Remain start is May 17 and I manually tried to change it but it's going back to May 17. What to do. Please help need it right away.

Member for

16 years 7 months

Sridevi,

 

Change the % complete type to physical. Then when you ammend the remaining duration, the % complete will not be adjusted.

Best practise is to use physical % complete by default for all activities, and only to use duration % complete when there is a direct relationship between % complete and remaining duration (which is rare).

 

Cheers,

 