Microsoft Project Member for 11 years 4 months Member for 11 years 4 months Submitted by Dan Martensson on Wed, 2014-06-25 15:17 Permalink Thank you! The problem got Thank you! The problem got slowed yesterday /Dan Member for 17 years 10 months Member for 17 years 10 months Submitted by Evgeny Z. on Wed, 2014-06-25 13:35 Permalink Dan,you need to create a Dan, you need to create a seporate calendar and assign it to this spesific task: See the link below: http://office.microsoft.com/en-gb/project-help/set-working-times-vacati… Consider also Task option "Scheduling ignors resource calendar" Regards. Member for 11 years 4 months Member for 11 years 4 months Submitted by Dan Martensson on Tue, 2014-06-24 09:50 Permalink Anyone? /Dan Anyone? /Dan Log in or register to post comments
Member for 11 years 4 months Member for 11 years 4 months Submitted by Dan Martensson on Wed, 2014-06-25 15:17 Permalink Thank you! The problem got Thank you! The problem got slowed yesterday /Dan
Member for 17 years 10 months Member for 17 years 10 months Submitted by Evgeny Z. on Wed, 2014-06-25 13:35 Permalink Dan,you need to create a Dan, you need to create a seporate calendar and assign it to this spesific task: See the link below: http://office.microsoft.com/en-gb/project-help/set-working-times-vacati… Consider also Task option "Scheduling ignors resource calendar" Regards.
Member for 11 years 4 months Member for 11 years 4 months Submitted by Dan Martensson on Tue, 2014-06-24 09:50 Permalink Anyone? /Dan Anyone? /Dan
Member for
11 years 4 monthsThank you! The problem got
Thank you!
The problem got slowed yesterday
/Dan
Member for
17 years 10 monthsDan,you need to create a
Dan,
you need to create a seporate calendar and assign it to this spesific task:
See the link below:
http://office.microsoft.com/en-gb/project-help/set-working-times-vacati…
Consider also Task option "Scheduling ignors resource calendar"
Regards.
Member for
11 years 4 monthsAnyone? /Dan
Anyone?
/Dan