If you want to see the baseline bars in seperate rows with start and end dates then there is a switch in > Format > Barchart > Baselines > Show Baselines on their Own Lines.
If you just want a different set of date columns then go to Table Definition and add two more columns for Start and Finish and in the Data Drop Down select the Baseline that you want.
You can also set a column to show the diference in days.
Member for
19 years 10 monthsHi Hemant Welcome to Planning
Hi Hemant
Welcome to Planning Planet
If you want to see the baseline bars in seperate rows with start and end dates then there is a switch in > Format > Barchart > Baselines > Show Baselines on their Own Lines.
If you just want a different set of date columns then go to Table Definition and add two more columns for Start and Finish and in the Data Drop Down select the Baseline that you want.
You can also set a column to show the diference in days.
Hope that helps
Best regards
Mike Testro
Member for
15 yearsWhat I meant was how to
What I meant was how to switch on the date columns with the "planned start" and "planned finish" dates. I have baselined the project already.