Planned Start

Member for

19 years 10 months

Hi Hemant

Welcome to Planning Planet

If you want to see the baseline bars in seperate rows with start and end dates then there is a switch in > Format > Barchart > Baselines > Show Baselines on their Own Lines.

If you just want a different set of date columns then go to Table Definition and add two more columns for Start and Finish and in the Data Drop Down select the Baseline that you want.

You can also set a column to show the diference in days.

Hope that helps

Best regards

Mike Testro

Member for

15 years

What I meant was how to switch on the date columns with the "planned start" and "planned finish" dates. I have baselined the project already.