FREE FLOAT in claims

Member for

18 years 5 months

Hi Francis



The EoT claim is to ask for an extension in Time for Completion i.e. the whole of the works and not individual activity. So, free float has no significance whatsoever in EoT claim.



Regards

Member for

19 years 10 months

Hi Francis



In my experience free float has little relevance in EOT claims.



It may have some fringe element in disruption claims but I have yet to come across a situation where it was relevant.



Someone else may have and I would like to hear about it.



Best regards



Mike Testro