I could link up the activities normally now except:-
1. is it necessary to update the "tool" -> "Schedule" for each activities since P3 would ask me to save the "Primavera Look" every time which is very troublesome?
2. How to fix the :start milestone" to a specific date since after i update the "schedule", it goes back to the data date everytime. How to determine an activities to a date without change?
Decide if a "milestone" is start or finish, then link it as a "task" activity; it will be slightly different if you are using "flag" activities, as they cannot have a successor.
what you say youve done is quite unclear; procedure is as follows:
a) link all activities as per your projects needs,
b) Click Tools, Schedule; enter the correct data date, it should be the project scheduled start date, after which all the activities bars will be moved; display the schedule report on screen as suggested by the sofwtare and check all the data agaisnt what you need to have.
I have linked all them up but any other box i need to input data to make it move forward?
Today, I found if i input the duration period accumulate from the data date, the bar could move outward, but I feel it is not sensible to do so since I cant calculate all activities!!!
Many thanks!
Shadowmoon
Member for
22 years 9 months
Member for22 years10 months
Submitted by Alexandre Faul… on Sat, 2007-12-08 11:27
the confusion for you may arise from the fact that P3 does not automatically schedule by default. You can change this, so it will act more like Suretrac or MSP but you will find that not having your activities running all over the place everytime you make a link or change a duration can be very soothing... ;)
Its also essential for larger plans, where the schedule update can take minutes, thus rendering plan editing impractical with auto-schedule on
Member for
18 years 1 month
Member for18 years2 months
Submitted by Johny Kesserwany on Thu, 2007-12-06 11:11
Member for
17 years 11 monthsRE: Progress bars not show Pls help!!!
Dear Brothers,
thank you very much!! i can do it now!!!
Regards,
Moon
Member for
17 years 10 monthsRE: Progress bars not show Pls help!!!
press F9 and give correct data date
Member for
18 years 1 monthRE: Progress bars not show Pls help!!!
Check your email
JK
Member for
17 years 11 monthsRE: Progress bars not show Pls help!!!
Dear Everybody,
I could finally adjust the bars with all of your help during the past few days!
i am trying how to resolve the automatically updating bar movement since the bars dont move after change of the duration.
Thank you so much!
shadowmoon
Member for
18 years 1 monthRE: Progress bars not show Pls help!!!
send your program over!!!
jkesser@hotmail.com
Member for
22 years 9 monthsRE: Progress bars not show Pls help!!!
Shadow moon,
1. press F9 on the keyboard instead of Tools, Schedule; you will skip the schedule report,
2. in the activity form, open Cons(traints) and enter a constraint date for the start milestone.
Alexandre
Member for
17 years 11 monthsRE: Progress bars not show Pls help!!!
Dear Friends,
I could link up the activities normally now except:-
1. is it necessary to update the "tool" -> "Schedule" for each activities since P3 would ask me to save the "Primavera Look" every time which is very troublesome?
2. How to fix the :start milestone" to a specific date since after i update the "schedule", it goes back to the data date everytime. How to determine an activities to a date without change?
My emai is colossu@netvigator.com
I could email you the P3 to you to read easily.
Thanks!!!
Shadowmoon
Member for
18 years 1 monthRE: Progress bars not show Pls help!!!
Hi Alexandre,
It seems that he had a loop!!!
JK
Member for
22 years 9 monthsRE: Progress bars not show Pls help!!!
Shadow moon,
Decide if a "milestone" is start or finish, then link it as a "task" activity; it will be slightly different if you are using "flag" activities, as they cannot have a successor.
What was your problem with scheduling?
Alexandre
Member for
17 years 11 monthsRE: Progress bars not show Pls help!!!
Dear All,
I finally success to link them up by your advice!!! ^O^
However, how to do for those milestone activities?
Thanks!! Many Thanks!!
Shadowmoon
Member for
18 years 1 monthRE: Progress bars not show Pls help!!!
Schedule command (Tools menu)
You should calculate a schedule each time you add or delete activities or revise their dates, durations, or relationships.
Is P3 gives you a Loop detected warning when scheduling?
JK
Member for
22 years 9 monthsRE: Progress bars not show Pls help!!!
Shadow Moon,
what you say youve done is quite unclear; procedure is as follows:
a) link all activities as per your projects needs,
b) Click Tools, Schedule; enter the correct data date, it should be the project scheduled start date, after which all the activities bars will be moved; display the schedule report on screen as suggested by the sofwtare and check all the data agaisnt what you need to have.
Hope it helps,
Alexandre
Member for
17 years 11 monthsRE: Progress bars not show Pls help!!!
Dear Alexandre and friends,
I have linked all them up but any other box i need to input data to make it move forward?
Today, I found if i input the duration period accumulate from the data date, the bar could move outward, but I feel it is not sensible to do so since I cant calculate all activities!!!
Many thanks!
Shadowmoon
Member for
22 years 9 monthsRE: Progress bars not show Pls help!!!
Are you sure the activities are properly linked together? Display the relationships to check this point.
Then, what is your data date?
Alexandre
Member for
17 years 11 monthsRE: Progress bars not show Pls help!!!
Dear All Brothers,
Thanks for your advices.
However, all activities stay on the data date as their start date but not extent forward....
Any other setting I need to check??
I havent seen such case in suretrak...
Member for
18 years 2 monthsRE: Progress bars not show Pls help!!!
indeed, welcome!
the confusion for you may arise from the fact that P3 does not automatically schedule by default. You can change this, so it will act more like Suretrac or MSP but you will find that not having your activities running all over the place everytime you make a link or change a duration can be very soothing... ;)
Its also essential for larger plans, where the schedule update can take minutes, thus rendering plan editing impractical with auto-schedule on
Member for
18 years 1 monthRE: Progress bars not show Pls help!!!
Run a Schedule!
F9 or Tools Schedule
Welcome to PP Shadow Moon!!!!
JK