Hi Anoon,



After such a long time.



But, then what do u say,



Issue a program with new dates without having a revision no. with no change in baseline giving a realistic view.



Is this what u say?



:-)



Raviraj

Member for

19 years 1 month

that’s the comparison between your Baseline/Target and your Current/Actual program which will give you a realistic view. Meaning, the Current or the Actual Program is always changeable and dynamic, but never do the changes in your Baseline or Target.

Member for

19 years 7 months

Hi Ravi,



IMO, the only way to modify the original programme (its logic and durations) is when u issue a revised one.



Regards,

Karim