thats the comparison between your Baseline/Target and your Current/Actual program which will give you a realistic view. Meaning, the Current or the Actual Program is always changeable and dynamic, but never do the changes in your Baseline or Target.
Member for
19 years 7 months
Member for19 years7 months
Submitted by Karim Mounir on Wed, 2007-09-19 11:18
Member for
18 years 5 monthsRE: Updating the program
Hi Anoon,
After such a long time.
But, then what do u say,
Issue a program with new dates without having a revision no. with no change in baseline giving a realistic view.
Is this what u say?
:-)
Raviraj
Member for
19 years 1 monthRE: Updating the program
thats the comparison between your Baseline/Target and your Current/Actual program which will give you a realistic view. Meaning, the Current or the Actual Program is always changeable and dynamic, but never do the changes in your Baseline or Target.
Member for
19 years 7 monthsRE: Updating the program
Hi Ravi,
IMO, the only way to modify the original programme (its logic and durations) is when u issue a revised one.
Regards,
Karim