Thanks vladimir,
I necked my activities succcessfully.
Maybe the option to display text in different positions relative to a bar in the gant chart could be included in the "Let's challenge spider" topic, P3 can do it.
Best regards,
Carlos.
Member for
24 years 9 months
Member for24 years9 months
Submitted by Vladimir Liberzon on Wed, 2010-09-29 09:17
if you want to neck Gantt Chart to show work time of any activity and assignment tick "Detailed Information" in the Levelling Options Dialog.
To select what to display in Gantt Chart select "Data on diagram" in Gantt Chart options and then the required field to be displayed. But you can show only one field at the right.
Unfortunately the pictures were not shown and I removed the reference.
Best Regards,
Vladimir
Member for
16 years 5 months
Member for16 years5 months
Submitted by Carlos Arana on Wed, 2010-09-29 05:24
Recommend you save your Diagrams and Tabular Reports as Template files so you can re-use them, same for your Layouts called configurations in Spider Project. Also learn how to transfer Layouts/Configurations and Reports among job files. It is unnecessary to recreate these once you created them one time.
Best Regards,
Rafael
Member for
16 years 5 months
Member for16 years5 months
Submitted by Carlos Arana on Thu, 2010-04-29 23:49
To show the diagram for any Gantt Chart line (for project, activity, project phase) right click on the line number or on the bar in the Gantt Chart.
In the poop-up menu select General Reports and Diagrams, the what do you want to show. For example select Resources, then choose what resorce to show, select what to show - work hours or quantities, then select an arrow that will move the selected resource from the left to the right window.
Select period (diagram may be shown per hour, day, week, month, etc), unselect cumulative.
On the next screen select the colors, if to show values and thats all.
To delete any diagram from the screen right click on it and select Delete Diagram.
In Spider Project right clicking on any object you will get pop-up menu thatt shows what can be done with this object.
By the way resource workload is calculated if to press Resource Peak Workload icon in the menu bar.
Member for
16 years 5 monthsThanks vladimir,I necked my
Thanks vladimir,
I necked my activities succcessfully.
Maybe the option to display text in different positions relative to a bar in the gant chart could be included in the "Let's challenge spider" topic, P3 can do it.
Best regards,
Carlos.
Member for
24 years 9 monthsHi Carlos,if you want to neck
Hi Carlos,
if you want to neck Gantt Chart to show work time of any activity and assignment tick "Detailed Information" in the Levelling Options Dialog.
To select what to display in Gantt Chart select "Data on diagram" in Gantt Chart options and then the required field to be displayed. But you can show only one field at the right.
Unfortunately the pictures were not shown and I removed the reference.
Best Regards,
Vladimir
Member for
16 years 5 monthsAbout the gantt display
Question 1:
Is there a way to "neck" the gantt bars to show non-work periods defined by calendars?
Question 2:
How do I choose the text to be displayed beside the gantt bars?
By default, it shows the activity name but I would like to display Volume [Remaining] on the right and Volume [Actual] on the left.
Member for
21 years 8 monthsRE: Layout
Carlos,
Recommend you save your Diagrams and Tabular Reports as Template files so you can re-use them, same for your Layouts called configurations in Spider Project. Also learn how to transfer Layouts/Configurations and Reports among job files. It is unnecessary to recreate these once you created them one time.
Best Regards,
Rafael
Member for
16 years 5 monthsRE: Layout
Thanks!
Member for
24 years 9 monthsRE: Layout
To show the diagram for any Gantt Chart line (for project, activity, project phase) right click on the line number or on the bar in the Gantt Chart.
In the poop-up menu select General Reports and Diagrams, the what do you want to show. For example select Resources, then choose what resorce to show, select what to show - work hours or quantities, then select an arrow that will move the selected resource from the left to the right window.
Select period (diagram may be shown per hour, day, week, month, etc), unselect cumulative.
On the next screen select the colors, if to show values and thats all.
To delete any diagram from the screen right click on it and select Delete Diagram.
In Spider Project right clicking on any object you will get pop-up menu thatt shows what can be done with this object.
By the way resource workload is calculated if to press Resource Peak Workload icon in the menu bar.
Best Regards,
Vladimir