Project Management Issues Discussion Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Fri, 2011-11-04 11:28 Permalink Hi Roy Khalil Wild Air is Hi Roy Khalil Wild Air is uncontrolled air generated when the MEP system is commissioned prior to balancing, to make it controlled subjected to user requirement Check MEP Testing and Commissioning specification to get more information for your claim analysis Regards Shahul Log in or register to post comments
Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Fri, 2011-11-04 11:28 Permalink Hi Roy Khalil Wild Air is Hi Roy Khalil Wild Air is uncontrolled air generated when the MEP system is commissioned prior to balancing, to make it controlled subjected to user requirement Check MEP Testing and Commissioning specification to get more information for your claim analysis Regards Shahul
Member for
16 years 11 monthsHi Roy Khalil Wild Air is
Hi Roy Khalil
Wild Air is uncontrolled air generated when the MEP system is commissioned prior to balancing, to make it controlled subjected to user requirement
Check MEP Testing and Commissioning specification to get more information for your claim analysis
Regards
Shahul