Since the baseline has actuals, then in Admin menu - Admin Preferences - Earned Value tab - Earned value claculation, select "Budgeted values with current dates" when calculating earned value from a baseline.
Hope the above works for you.
Best regards,
R. Catalan
Member for
18 years 6 months
Member for18 years6 months
Submitted by Oliver Melling on Fri, 2010-09-03 11:19
It wont calculate the SPI correctly when there is progress on the baseline.
You will notice that the bars in the gantt dont align properly either, but this can be altered by doing a global change to make the planned start/finish equal the start/finish dates (on the baseline programme).
However, i dont believe it is possible to change the cost profile that is used for calulating the SPI...which is why progressed baselines give an unexpected answer...makes me feel sick...but even project can do it.
Member for
19 years 6 months
Member for19 years6 months
Submitted by Nigel Winkley on Thu, 2010-08-12 06:19
Member for
18 years 6 monthsRE: Earned Value
Sonia,
Just note what Mr.Catalan has stated will work, but will also affect how EV is calculated on all projects within your database!
Member for
20 years 2 monthsRE: Earned Value
Hi Sonia,
Since the baseline has actuals, then in Admin menu - Admin Preferences - Earned Value tab - Earned value claculation, select "Budgeted values with current dates" when calculating earned value from a baseline.
Hope the above works for you.
Best regards,
R. Catalan
Member for
18 years 6 monthsRE: Earned Value
This is a problem with Primavera.
It wont calculate the SPI correctly when there is progress on the baseline.
You will notice that the bars in the gantt dont align properly either, but this can be altered by doing a global change to make the planned start/finish equal the start/finish dates (on the baseline programme).
However, i dont believe it is possible to change the cost profile that is used for calulating the SPI...which is why progressed baselines give an unexpected answer...makes me feel sick...but even project can do it.
Member for
19 years 6 monthsRE: Earned Value
If you are using P3e, check that your PHYSICAL percentage complete is correct. It should actual cost over budgeted cost expressed as a percentage.
Could also use cost at completion if the costs are different...
We use it here at NR and it works well.
Hope this helps
Nige
Member for
18 years 6 monthsRE: Earned Value
Depends what software you are using?