Oracle Primavera - PM6 Member for 13 years 9 months Member for 13 years 9 months Submitted by pidoylyn on Wed, 2012-02-29 08:05 Permalink Try go to the Projects Try go to the Projects Details, Resources tab, and tick the Resources can edit activity assignment percent complete.. Hope this can help. Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Tue, 2012-02-28 12:04 Permalink Dave, Make the Max Units/Time Dave, Make the Max Units/Time of the resource the same as the previous. Hope this will help. Log in or register to post comments
Member for 13 years 9 months Member for 13 years 9 months Submitted by pidoylyn on Wed, 2012-02-29 08:05 Permalink Try go to the Projects Try go to the Projects Details, Resources tab, and tick the Resources can edit activity assignment percent complete.. Hope this can help.
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Tue, 2012-02-28 12:04 Permalink Dave, Make the Max Units/Time Dave, Make the Max Units/Time of the resource the same as the previous. Hope this will help.
Member for
13 years 9 monthsTry go to the Projects
Try go to the Projects Details, Resources tab, and tick the Resources can edit activity assignment percent complete..
Hope this can help.
Member for
15 years 11 monthsDave, Make the Max Units/Time
Dave,
Make the Max Units/Time of the resource the same as the previous.
Hope this will help.