Oracle Primavera - PM6 Member for 17 years 3 months Member for 17 years 3 months Submitted by Muhammad Fiaz on Wed, 2008-08-27 23:40 Permalink RE: Progress by units in P5 Thanks for your reply. If we define BOQ as Non-Labor and Manhour as Labor resource then while updating progress by units P5 calculates by adding both units as %completed = actaul (Labour+NonLbour) units/Budgeted(Labor+Nonlabour units) Budgeted BOQ=4000 Sqft , Mhrs=250 Actual BOQ=2000 Sqft , Mhrs=100 Progress( by units ) calcuted by P5 is (2000+100)/(2000+250)=49.41% But actually BOQ is 2000/4000=50% How can we update progress on BOQ Nonlabour resource units only and planned Labour Manohours units depending on BOQ.I want to update progress by BOQ . Please advise. Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Tue, 2008-08-26 09:41 Permalink RE: Progress by units in P5 The other way round. Labour - productive work (especially physical work done for wages) Log in or register to post comments
Member for 17 years 3 months Member for 17 years 3 months Submitted by Muhammad Fiaz on Wed, 2008-08-27 23:40 Permalink RE: Progress by units in P5 Thanks for your reply. If we define BOQ as Non-Labor and Manhour as Labor resource then while updating progress by units P5 calculates by adding both units as %completed = actaul (Labour+NonLbour) units/Budgeted(Labor+Nonlabour units) Budgeted BOQ=4000 Sqft , Mhrs=250 Actual BOQ=2000 Sqft , Mhrs=100 Progress( by units ) calcuted by P5 is (2000+100)/(2000+250)=49.41% But actually BOQ is 2000/4000=50% How can we update progress on BOQ Nonlabour resource units only and planned Labour Manohours units depending on BOQ.I want to update progress by BOQ . Please advise.
Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Tue, 2008-08-26 09:41 Permalink RE: Progress by units in P5 The other way round. Labour - productive work (especially physical work done for wages)
Member for
17 years 3 monthsRE: Progress by units in P5
Thanks for your reply.
If we define BOQ as Non-Labor and Manhour as Labor resource then while updating progress by units P5 calculates by adding both units as
%completed = actaul (Labour+NonLbour) units/Budgeted(Labor+Nonlabour units)
Budgeted BOQ=4000 Sqft , Mhrs=250
Actual BOQ=2000 Sqft , Mhrs=100
Progress( by units ) calcuted by P5 is
(2000+100)/(2000+250)=49.41%
But actually BOQ is 2000/4000=50%
How can we update progress on BOQ Nonlabour resource units only and planned Labour Manohours units depending on BOQ.I want to update progress by BOQ .
Please advise.
Member for
18 years 6 monthsRE: Progress by units in P5
The other way round.
Labour - productive work (especially physical work done for wages)