P3e version 5- Baseline problems

Member for

17 years 3 months

Dieter Wambach,



Thanks for the reply :). I will try to propose this to my company to use P6 if possible. At the moment , I always encountered this baseline problems/inconsistencies everytime!



**Norul**

Member for

18 years 9 months

Prem

This item is solved in P6, so you can copy BLs together with the project. During the call for copy there is a screen where you can select those BL to copy and those for not.

Dieter

Member for

20 years 8 months

but why exporting baseline is not copied along with the project even in P6

Member for

18 years 9 months

Norul

This is solved in P6. In P5, baselines were not copied together with a project.

You have to ways: Upgrade to P6 or unlink ("Restore") the BL --> Copy project + BL --> create BL again out of this BL-project.

Regards

Dieter