Combine 2 Projects folder in 1 Project

Member for

21 years 9 months

i tried it to open 2 projects but i can’t link activities to the other activities of different open project schedule and the grouping is different from the other (my grouping is in project level not global)

Member for

21 years

Team,



Remember when you open more than one project to schedule/level that EACH project has a float path.



If you need to process multiple projects so that they only have one float path each project must have its "Must Finish by" date set to the same value. Leaving the date blank will not do

Member for

18 years 9 months

Pacifico

If you open both (or more) projects, common scheduling is no problem. The data date should be the same down to the minutes.

Automatted resource-levelling we don’t use, so I have no experience.

Regards

Dieter